Task does not allow multiple incoming sequence flow (uncontrolled flow)
Issue
- According to BPMN 2.0 specification allows on page 153 multiple incoming flow sequences for activities (i.e. also for tasks). jBPM fails to validate such an BPMN file. It throws an
IllegalArgumentExceptionwith the messageThis type of node cannot have more than one incoming connection!. jBPM Web Designerand the Eclipse BPMN2 modellerBPMN2 Diagram Editorcurrently does not allow multiple incoming connections forUser Task. How to do that?
Environment
- Red Hat JBoss BPM Suite (BPMS)
- 6.x
- Red Hat JBoss BRMS (BRMS)
- 6.x
- Red Hat JBoss Developer Studio (JBDS)
- 7.x