Fuse 6.3 camel quartz cron endpoint triggers immediately on failover

Solution Verified - Updated -

Issue

In a fabric environment, the quartz component fires immediately after container failover (using a master: endpoint). The quartz component should instead fire at the next scheduled cron time. For example:

<from uri="master:foo:quartz://mygroup/mytrigger?cron=0/15/30/45+*+*+*+*+?" />

Environment

  • Red Hat JBoss Fuse
    • 6.3.x

Subscriber exclusive content