By default, routes are automatically started when your
Apache Camel application (as represented by the
CamelContext instance) starts up and routes are
automatically shut down when your Apache Camel application shuts
down. For non-critical deployments, the details of the shutdown
sequence are usually not very important. But in a production
environment, it is often crucial that existing tasks should run
to completion during shutdown, in order to avoid data loss. You
typically also want to control the order in which routes shut
down, so that dependencies are not violated (which would prevent
existing tasks from running to completion).
For this reason, Apache Camel provides a set of features to support graceful shutdown of applications. Graceful shutdown gives you full control over the stopping and starting of routes, enabling you to control the shutdown order of routes and enabling current tasks to run to completion.
It is good practice to assign a route ID to each of your routes. As well as making logging messages and management features more informative, the use of route IDs enables you to apply greater control over the stopping and starting of routes.
For example, in the Java DSL, you can assign the route ID,
myCustomerRouteId, to a route by invoking the
routeId() command as follows:
from("SourceURI").routeId("myCustomRouteId").process(...).to(TargetURI);In the XML DSL, set the route element's
id attribute, as follows:
<camelContext id="CamelContextID" xmlns="http://camel.apache.org/schema/spring"> <route id="myCustomRouteId" > <from uri="SourceURI"/> <process ref="someProcessorId"/> <to uri="TargetURI"/> </route> </camelContext>
By default, all of the routes that the CamelContext knows about at start time will be started automatically. If you want to control the start-up of a particular route manually, however, you might prefer to disable automatic start-up for that route.
To control whether a Java DSL route starts up automatically,
invoke the autoStartup command, either with a
boolean argument (true or
false) or a String argument
(true or false). For example, you
can disable automatic start-up of a route in the Java DSL, as
follows:
from("SourceURI")
.routeId("nonAuto")
.autoStartup(false)
.to(TargetURI);You can disable automatic start-up of a route in the XML DSL
by setting the autoStartup attribute to
false on the route element, as
follows:
<camelContext id="CamelContextID" xmlns="http://camel.apache.org/schema/spring"> <route id="nonAuto" autoStartup="false"> <from uri="SourceURI"/> <to uri="TargetURI"/> </route> </camelContext>
You can manually start or stop a route at any time in Java by
invoking the startRoute() and
stopRoute() methods on the
CamelContext instance. For example, to start
the route having the route ID, nonAuto, invoke the
startRoute() method on the
CamelContext instance, context, as
follows:
// Java
context.startRoute("nonAuto");To stop the route having the route ID, nonAuto,
invoke the stopRoute() method on the
CamelContext instance, context, as
follows:
// Java
context.stopRoute("nonAuto");
By default, Apache Camel starts up routes in a non-deterministic
order. In some applications, however, it can be important to
control the startup order. To control the startup order in the
Java DSL, use the startupOrder() command, which
takes a positive integer value as its argument. The route with
the lowest integer value starts first, followed by the routes
with successively higher startup order values.
For example, the first two routes in the following example are
linked together through the seda:buffer endpoint.
You can ensure that the first route segment starts
after the second route segment by
assigning startup orders (2 and 1 respectively), as
follows:
Example 6. Startup Order in Java DSL
from("jetty:http://fooserver:8080")
.routeId("first")
.startupOrder(2)
.to("seda:buffer");
from("seda:buffer")
.routeId("second")
.startupOrder(1)
.to("mock:result");
// This route's startup order is unspecified
from("jms:queue:foo").to("jms:queue:bar");Or in Spring XML, you can achieve the same effect by setting
the route element's startupOrder
attribute, as follows:
Example 7. Startup Order in XML DSL
<route id="first" startupOrder="2">
<from uri="jetty:http://fooserver:8080"/>
<to uri="seda:buffer"/>
</route>
<route id="second" startupOrder="1">
<from uri="seda:buffer"/>
<to uri="mock:result"/>
</route>
<!-- This route's startup order is unspecified -->
<route>
<from uri="jms:queue:foo"/>
<to uri="jms:queue:bar"/>
</route>Each route must be assigned a unique startup order value. You can choose any positive integer value that is less than 1000. Values of 1000 and over are reserved for Apache Camel, which automatically assigns these values to routes without an explicit startup value. For example, the last route in the preceding example would automatically be assigned the startup value, 1000 (so it starts up after the first two routes).
When a CamelContext instance is shutting down,
Apache Camel controls the shutdown sequence using a pluggable
shutdown strategy. The default
shutdown strategy implements the following shutdown
sequence:
Routes are shut down in the reverse of the start-up order.
Normally, the shutdown strategy waits until the currently active exchanges have finshed processing. The treatment of running tasks is configurable, however.
Overall, the shutdown sequence is bound by a timeout (default, 300 seconds). If the shutdown sequence exceeds this timeout, the shutdown strategy will force shutdown to occur, even if some tasks are still running.
Routes are shut down in the reverse of the start-up order.
That is, when a start-up order is defined using the
startupOrder() command (in Java DSL) or
startupOrder attribute (in XML DSL), the first
route to shut down is the route with the
highest integer value assigned by the
start-up order and the last route to shut down is the route with
the lowest integer value assigned by the
start-up order.
For example, in Example 6, the
first route segment to be shut down is the route with the ID,
first, and the second route segment to be shut
down is the route with the ID, second. This example
illustrates a general rule, which you should observe when
shutting down routes: the routes that expose
externally-accessible consumer endpoints should be shut down
first, because this helps to throttle the flow of
messages through the rest of the route graph.
![]() | Note |
|---|---|
Apache Camel also provides the option
|
If a route is still processing messages when the shutdown
starts, the shutdown strategy normally waits until the currently
active exchange has finished processing before shutting down the
route. This behavior can be configured on each route using the
shutdownRunningTask option, which can take
either of the following values:
-
ShutdownRunningTask.CompleteCurrentTaskOnly (Default) Usually, a route operates on just a single message at a time, so you can safely shut down the route after the current task has completed.
-
ShutdownRunningTask.CompleteAllTasks Specify this option in order to shut down batch consumers gracefully. Some consumer endpoints (for example, File, FTP, Mail, iBATIS, and JPA) operate on a batch of messages at a time. For these endpoints, it is more appropriate to wait until all of the messages in the current batch have completed.
For example, to shut down a File consumer endpoint gracefully,
you should specify the CompleteAllTasks option, as
shown in the following Java DSL fragment:
// Java
public void configure() throws Exception {
from("file:target/pending")
.routeId("first").startupOrder(2)
.shutdownRunningTask(ShutdownRunningTask.CompleteAllTasks)
.delay(1000).to("seda:foo");
from("seda:foo")
.routeId("second").startupOrder(1)
.to("mock:bar");
}The same route can be defined in the XML DSL as follows:
<camelContext id="camel" xmlns="http://camel.apache.org/schema/spring">
<!-- let this route complete all its pending messages when asked to shut down -->
<route id="first"
startupOrder="2"
shutdownRunningTask="CompleteAllTasks">
<from uri="file:target/pending"/>
<delay><constant>1000</constant></delay>
<to uri="seda:foo"/>
</route>
<route id="second" startupOrder="1">
<from uri="seda:foo"/>
<to uri="mock:bar"/>
</route>
</camelContext>The shutdown timeout has a default value of 300 seconds. You
can change the value of the timeout by invoking the
setTimeout() method on the shutdown strategy.
For example, you can change the timeout value to 600 seconds, as
follows:
// Java // context = CamelContext instance context.getShutdownStrategy().setTimeout(600);
If you are implementing a custom Apache Camel component (which also
inherits from the org.apache.camel.Service
interface), you can ensure that your custom code receives a
shutdown notification by implementing the
org.apache.camel.spi.ShutdownPrepared
interface. This gives the component an opportunity execute
custom code in preparation for shutdown.






![[Note]](imagesdb/note.gif)